Skip to content
ASME U & R Stamp · TEMA · NQA-1 Quality Program Call us: 800-767-9507
Harris Thermal
Products & Services Overview Shell & Tube Heat Exchangers Pressure Vessels / Tanks Other Fabrication Machining / Drilling Repairs
Industries Overview Oil & Gas Chemical Formaldehyde & Resins Pulp & Paper Food Processing Mining & Minerals Power Generation Nuclear Data Centers Water Treatment Sugar Processing LNG General Manufacturing
Capabilities Overview Fabrication Machining Materials Engineering Quality Control Safety Logistics & Shipping
Resources
About About Us Certifications Employment
Contact Get a Quote →
Home / Industry Insights / Postweld heat treatment of pressure vessels: requirements, limitations, and fabrication planning

Postweld heat treatment of pressure vessels: requirements, limitations, and fabrication planning

Published

Postweld heat treatment of pressure vessels can unsettle a fabrication plan that looked complete on paper. A carbon steel vessel meets its design pressure and temperature, the drawings are approved, and then the owner's specification adds PWHT. With nozzles, saddles and lifting lugs counted, the completed assembly no longer fits the furnace the estimate assumed.

Method, weld sequence, hold points and perhaps geometry now need revisiting, along with material certification, procedure qualification, cost and lead time. Not every pressure vessel requires PWHT. Where one does, it is a design and fabrication constraint rather than a final manufacturing step, and it belongs in the RFQ.

IN BRIEF

  • PWHT can be required by the Code, the owner or a service standard, and meeting one does not satisfy the others.

  • No single thickness decides Code applicability. Material group, Code-defined nominal thickness, weld type, preheat, service and edition all matter.

  • The alloy sets the cycle. Stress relief suited to carbon steel can sensitize some stainless steels and embrittle duplex grades.

  • Furnace fit is measured around nozzles, supports and lifting attachments, and local PWHT needs both Code and owner acceptance.

  • PWHT added after quotation can change weld sequence, qualifications, material certification and delivery.

On this page: what PWHT does · when it is required · materials · welding procedures · furnace and local PWHT · furnace fit · temperature and inspection · scheduling · common mistakes · RFQ checklist · Harris Thermal · FAQs

What is postweld heat treatment, and what does it do?

Welding melts a narrow band of metal while the surrounding material stays cool. As the weld shrinks, that material restrains it, leaving residual stresses that can approach yield strength in highly restrained joints, and hardenable steels can form hard heat-affected zone (HAZ) microstructures.

Postweld heat treatment, often called pressure vessel stress relief, reheats the weldment below its lower transformation temperature, holds it and cools it under control. Yield strength falls as temperature rises, so residual stresses relax by creep, and in many ferritic steels the cycle also tempers hard weld and HAZ microstructures. The aims are lower brittle fracture and cracking risk, plus dimensional stability.

The limits matter too:

  • Residual stress is reduced but not eliminated. Fitness-for-service reference values for furnace-treated carbon steel welds still assume a fraction of yield strength, as Equity Engineering notes.

  • Fatigue strength of as-welded joints improves little.

  • Cracks are not repaired. Hydrogen cracking is controlled by preheat, low-hydrogen practice and, where specified, a separate hydrogen-release post-heat.

  • Overtreatment can lower strength, for example above a steel's original tempering temperature.

Normalizing and full annealing heat ferritic steel above its upper transformation temperature, and solution annealing dissolves precipitates in stainless steels and nickel alloys before rapid cooling. All three are different operations. An order that only says "stress relieve" leaves the cycle undefined, and the National Board cautions that poorly performed heat treatment can do more harm than good.

When is PWHT required by Code, owner or service?

PWHT can be required by the construction Code, the owner's or licensor's specification, or service standards that specification invokes, and each source is checked separately.

Code-required PWHT

ASME PWHT requirements for carbon and low-alloy steels under Section VIII, Division 1 sit in UCS-56. Its tables set minimum holding temperatures and times by P-Number and Group Number, their notes list conditional PWHT exemptions, and UW-40 defines the procedures. Applicability can turn on:

  • P-Number and Group Number

  • nominal thickness as UW-40(f) defines it for the joint, including corrosion allowance

  • weld type, configuration and welding process

  • preheat, which some exemptions require

  • service, such as lethal service, where carbon and low-alloy steel vessels require PWHT

  • the Code edition named in the contract

Nominal thickness is defined joint by joint, for example as groove depth, fillet throat or the thinner of two butt-welded parts, and it can differ from plate thickness. Exemptions carry their own conditions, and some do not apply when PWHT is a service requirement. Division 2, an alternative construction Code, has separate PWHT rules.

Owner- and project-specified PWHT

Owners and EPC contractors often require PWHT beyond the Code minimum for service severity, hardness control, cracking resistance or reliability. IOGP's supplementary specification for shell-and-tube exchangers asks on its data sheet whether PWHT is required for process reasons on each side. One national oil company's published vessel specification requires Cr-Mo PWHT in all thicknesses and whole-vessel treatment in an enclosed furnace. Because such requirements are contractual, Code thickness exemptions do not relax them.

Service-related requirements

Service standards treat PWHT as one control among several:

  • Wet H2S. AMPP SP0472 addresses weld hardness, and AMPP SP21534-2024 covers fabrication of new carbon steel vessels for refinery wet H2S service. API RP 571 describes PWHT as effective against sulfide stress cracking, partly effective against stress-oriented hydrogen-induced cracking, and unable to prevent hydrogen-induced cracking or blistering.

  • Amine. API RP 945 (4th edition, 2022) guides PWHT of carbon steel against amine stress corrosion cracking and moved earlier amine-specific guidelines to an annex, so specifications should state their basis. The same chemistry appears in solvent-based carbon capture systems.

  • High-temperature hydrogen. API RP 941 gives separate Nelson curves for carbon steel with and without PWHT. The Chemical Safety Board warns that the non-PWHT curve misses conditions under which carbon steel failed at Tesoro Anacortes, and it urges inherently safer materials.

  • Cyclic service. PWHT does little for as-welded fatigue strength, so detail design and weld quality govern.

How does material selection change PWHT requirements?

The alloy decides what a thermal cycle does, so the cycle has to suit every material in the heated zone, including internals, cladding and overlay.

MaterialWhy PWHT may be required or consideredMain risks from the cycleVerify before specifying a cycle
Carbon steelsCode thickness and service rules; owner requirements for amine, wet H2S, caustic or lethal service; dimensional stabilityLong or repeated cycles can lower strength and toughness; plate tested without simulated PWHT may not represent the finished vesselApplicable table and notes; service basis; simulated-PWHT testing of plate; procedure qualification for total time at temperature
Low-alloy and Cr-Mo steelsTempering hardenable weld metal and HAZ; restoring toughness; Code rules for these P-NumbersUnder-tempering if too cool; exceeding the lower critical temperature if too hot; reheat cracking in susceptible gradesGrade-specific temperature window; filler metal chemistry; heating rates; intermediate or hydrogen-release treatments
Austenitic stainless steelsDivision 1 neither requires nor prohibits stress relief; occasionally specified for dimensional stability or stress corrosion concernsSensitization of standard-carbon grades in the stress-relief range; distortion; stress relief is not equivalent to solution annealingL or stabilized grade; intergranular corrosion testing; exposure when attached to carbon steel that requires PWHT
Duplex and super duplex stainless steelsConventional stress-relief PWHT is generally avoided because harmful phases may form. Where postweld heat treatment is necessary, the appropriate treatment must be established for the specific alloy, fabrication, and applicable requirements.Intermetallic and other precipitates that reduce toughness and corrosion resistanceWhether any treatment is needed; sequencing that keeps duplex parts out of carbon steel PWHT; producer guidance
Nickel alloysAlloy-specific: most corrosion-resistant grades are used as-welded; precipitation-strengthened grades need specified heat treatmentIntermediate-temperature exposure can precipitate phases that reduce corrosion resistanceProducer heat-treatment guidance for the exact alloy; effect of any carbon steel PWHT on attached alloy parts
Dissimilar-metal welds and clad constructionThe ferritic side's requirement and the higher PWHT temperature governCarbon migration across the fusion line; thermal expansion mismatch; changes to cladding or overlay chemistryBoth base metals and the filler; buttering sequence; procedure qualification in the PWHT condition

Table 1. PWHT considerations by material family. Temperatures and times come from the governing Code edition and producer data.

Plate for a heat-treated vessel may need tests after a simulated PWHT cycle, and some HIC-tested plate is guaranteed only in the PWHT condition. In Grade 91 weld metal, manganese and nickel lower the transformation temperature that caps the PWHT range. IMOA advises against stress relief of duplex grades because intermetallic phases can form, and Haynes advises avoiding intermediate-temperature PWHT for most of its alloys.

For dissimilar joints, PWHT can drive carbon from the ferritic side toward the fusion line. One established sequence is to butter the ferritic part, heat treat it, then make the final weld. Clad construction and exotic alloy heat exchangers need the same check on the corrosion-resistant layer.

How do welding procedures affect PWHT planning?

Because Code thickness is assessed weld by weld, a nozzle, tubesheet connection or attachment can govern instead of the shell. Groove, fillet, tube-to-tubesheet and attachment welds each have their own definitions and exemption conditions.

Welding procedure qualification

ASME Section IX treats PWHT as an essential variable, so a procedure qualified without PWHT does not cover welds that receive it, or the reverse. For most ferrous P-Numbers, treatment below the lower transformation temperature is qualified separately from treatment above it. Where toughness testing applies, the coupon's time at temperature must represent production, including extra cycles. Filler metals should be certified for the same condition.

Repairs and later attachments

Division 1 requires PWHT, where it applies, after weld repairs and before the hydrostatic test, with limited alternatives for certain repairs to some carbon and low-alloy steels. A clip, pad or nozzle welded later may need another cycle, which must stay within the procedure qualifications and the simulated-PWHT time on the material certificates.

Illustrative example, not a Code determination. An exchanger's shell seams fall within an exemption, so the estimate assumes no PWHT. A revision adds a large nozzle with a heavy neck and reinforcement. Whether that weld now needs PWHT depends on how UW-40(f) defines nominal thickness for the detail. If it does, local PWHT in a cylindrical shell generally means a full-circumference band, attachments in that band must be welded first, and the procedure must be qualified with PWHT. Checking governing thickness joint by joint during design catches this.

How do full-furnace and local PWHT compare?

UW-40 permits several approaches: the complete vessel in a furnace, the vessel in overlapping heats, sections treated before final assembly, internal heating, and local heating under defined conditions.

AttributeFull-furnace PWHTLocal PWHT
What is heatedThe complete vessel or subassembly, or the vessel in overlapping heatsA soak band around the weld, with heated and gradient-control bands beyond it
Temperature uniformityGenerally the most uniform; zone control helps where thickness variesAxial and through-thickness gradients; the inside surface can run cooler than the outside
Heating and coolingRates and hold set for the whole chargeRates controlled at the band; uneven heating can create new residual stress
Capacity and geometryLimited by the furnace door, interior, car or hearth capacity and loading equipmentNo furnace limit, but in a cylindrical shell a nozzle generally needs a full-circumference band
Support and distortionThe whole vessel loses strength at temperature; shaped supports and sometimes internal stiffening are neededThe hot band is restrained by cooler metal; sagging or out-of-roundness can develop at the band
Temperature recordsThermocouples on the vessel; furnace air temperature is not proofThermocouples at the weld, band edges and, where possible, the opposite surface
AcceptanceThe baseline method; some owners require itMust suit the joint under the Code and be accepted by the owner; WRC 452 compliance does not guarantee furnace-equivalent stress relief

Table 2. Full-furnace and local PWHT compared. Band widths and temperature limits come from the governing Code edition and the heat-treatment procedure.

A vessel that fits no available furnace is not automatically a candidate for local PWHT. Division 1 restricts where local methods apply, owners may prohibit them, and the relief achieved can differ. In Equity Engineering's 2026 case study, a local treatment fully compliant with WRC Bulletin 452 left residual stresses well above furnace-equivalent values, which matters most where cracking resistance is the reason for PWHT. WRC 452 was issued in a second edition in June 2026.

Staged fabrication

Large vessels are sometimes heat treated in sections, with closing seams treated locally. Each section's PWHT covers only the welds it contained, so closing seams, later nozzles and repairs need their own evaluation, and double-cycled overlap zones must be covered by qualifications and material certification.

Will the vessel fit the furnace?

PWHT furnace limitations start with the usable envelope. It is smaller than the nominal dimensions once the door, car, burners, insulation and thermocouple access are counted, and gas must circulate without flame touching the vessel. The vessel's envelope includes:

  • shell outside diameter plus nozzle projections and flanges

  • saddles, skirts, legs and lifting lugs

  • overall length, including heads and head nozzles

  • supports or stiffening needed during the cycle

  • weight against car and loading capacity

A shell diameter equal to a furnace's nominal width leaves no room for supports, circulation or projections.

In-house and externally coordinated PWHT

When a vessel exceeds a fabricator's own furnace, PWHT may move to an outside heat-treatment provider. The vessel is then braced and moved both ways, furnace time is booked around the provider's schedule, and hold points and witness requirements travel with it. The provider's procedure, thermocouple layout and charts join the manufacturer's records, because the certifying manufacturer signs the data report. An outside furnace is not a guaranteed fit, so dimensions, weight, handling and schedule are confirmed for each configuration.

If no furnace fits, the options are design changes, multiple heats, staged fabrication or local treatment, each subject to the Code, the owner and the geometry. A thickness-driven Code requirement can sometimes be designed around. A service-driven one cannot.

How are temperature, distortion and inspection controlled?

Division 1 sets a minimum holding temperature and a thickness-based holding time, and limits heating and cooling rates and temperature differences across the part. Owners may add a maximum temperature, a narrower range or hardness checks.

Thermocouples attached to the vessel control and record the cycle, because furnace air temperature does not prove the steel reached temperature. They should represent thick and thin sections, nozzles and the top and bottom of the load, and their charts become permanent records.

At holding temperature steel loses much of its strength, and a vessel may not carry its own weight. Asymmetric fabrications, heavy nozzles and uneven thickness heat and cool unevenly and can distort. Shaped supports, internal stiffening, controlled rates and dimensional checks afterward manage the risk, and machined faces are generally finished after PWHT where practical.

Inspection and testing sequence

PWHT, when required, precedes the final hydrostatic test, and Division 1 permits a preliminary leak test beforehand. The inspection and test plan should state which examinations follow PWHT, since specifications may require some afterward where delayed or reheat cracking is a concern. Hardness testing usually comes from a service standard or owner specification that defines method, locations and acceptance. On nuclear and DOE work, NQA-1 quality assurance formalizes the traceability linking each weld to its procedure, cycle and examinations.

How does PWHT affect the fabrication schedule?

PWHT divides fabrication into before and after. Everything welded to the pressure boundary that must be treated has to be complete first, and examination, repairs and the hydrostatic test are arranged around the cycle. Schedule-critical items include:

  • approval of the PWHT basis, method and sequence

  • plate certified after simulated PWHT

  • procedure qualification and welding sequence

  • furnace time, in-house or external, and transport

  • inspection hold points and witness requirements

  • repair, re-treatment and re-examination loops

A requirement added after quotation can force requalification, new material certification, design changes and external furnace bookings, none of which appears in a quote prepared without PWHT.

Illustrative scenario

Illustrative scenario, not a project record. A large carbon steel vessel is quoted without PWHT. A later owner specification requires PWHT for process reasons, and with nozzles and saddles in place the assembly exceeds the in-house furnace envelope. Five questions follow:

  1. Basis. Is PWHT a service requirement, and are local or staged methods allowed?

  2. Geometry. Can nozzle orientation, projections or supports change to fit an available furnace? Welded saddles cannot simply be added after treatment.

  3. Method. Would multiple heats, heat-treated sections or an external furnace work, and would the Code and owner accept each?

  4. Welding and materials. Do qualifications and material certificates cover the PWHT condition and total time at temperature?

  5. Logistics. What do transport, furnace booking and resequenced examination do to cost and delivery?

Any of these may resolve the problem, or none may, depending on the specification, the geometry and the equipment actually available.

What are the most common PWHT specification mistakes?

  • Assuming every ASME vessel needs PWHT. Material, thickness, weld type and service decide.

  • Relying on one thickness threshold. Limits vary by P-Number, weld type and Code.

  • Overlooking owner and licensor requirements, including PWHT for process reasons.

  • Skipping alloy checks for stainless, duplex and overlay in the heated zone.

  • Checking shell diameter instead of the full envelope.

  • Treating local PWHT as automatic when a vessel will not fit a furnace.

  • Welding after PWHT without evaluating re-treatment.

  • Leaving WPS and PQR coverage unchecked for the PWHT condition and time at temperature.

  • Omitting inspection, hardness and record requirements.

  • Raising PWHT after quotation, when sequence and materials are fixed.

What PWHT information should an RFQ include?

The first list establishes whether PWHT applies; the second lets the fabricator plan and price it. Division 1's optional user's design requirements form, Form U-DR-1, is one way to record them.

To establish whether PWHT applies

  • Construction Code, Division and edition

  • Design pressure, design temperature and minimum design metal temperature

  • Material specifications and grades, including welded attachments

  • Thicknesses, including corrosion allowance

  • Weld joint types and configurations, including nozzle, tubesheet and attachment details

  • Process service and cracking concerns: lethal, wet H2S, amine, caustic, hydrogen or cyclic

  • Owner, licensor or EPC specifications, including PWHT for process reasons

  • PWHT requirements and any Code exemptions the purchaser excludes

To plan fabrication and quotation

  • Whether local, multi-heat or staged PWHT is acceptable

  • Overall dimensions with nozzle projections, supports and lifting attachments, and weight

  • Inspection and testing requirements, including examinations after PWHT

  • Hardness testing method, locations and acceptance criteria, where applicable

  • Welding procedure qualification requirements, including toughness testing and PWHT cycles

  • Material certification, including simulated PWHT

  • Required heat-treatment records, such as time-temperature charts and thermocouple maps

  • Transportation and delivery constraints

  • The engineer responsible for the PWHT basis, and who approves deviations

How Harris Thermal plans for PWHT in pressure vessel fabrication

Harris Thermal designs and fabricates custom ASME Section VIII, Division 1 pressure vessels, shell-and-tube heat exchangers, condensers, evaporators and other industrial process equipment in Newberg, Oregon, with in-house thermal and mechanical design within that scope. Process design stays with the owner or EPC, and the PWHT basis comes from the governing Code, the purchase specification and the responsible engineer.

When PWHT applies, Harris plans material and thickness, weld details, procedure qualification, the furnace envelope, fabrication sequence, hold points and delivery together during design and estimating. Harris has an in-house PWHT oven. For larger equipment, or where a project requires external heat treatment, Harris can coordinate PWHT with an outside heat-treatment provider, subject to equipment dimensions, handling limitations, scheduling and project requirements. Examination and testing are sequenced around whichever route a vessel takes.

Sharing the PWHT basis, service, materials and a dimensioned outline with the RFQ lets the method be confirmed before you receive a quotation.

FAQs about postweld heat treatment of pressure vessels

When is PWHT required for an ASME Section VIII pressure vessel?

Under Division 1, it depends on P-Number and Group Number, the Code-defined nominal thickness of each weld, weld type and process, preheat, service such as lethal service, and the Code edition. Owner specifications and service standards can require PWHT where the Code does not.

What does postweld heat treatment do to a welded vessel?

It relaxes welding residual stress and, in many ferritic steels, tempers hard weld and HAZ microstructures, lowering brittle fracture and environmental cracking risk. It does not eliminate residual stress, repair cracks or substantially improve as-welded fatigue strength.

Do stainless steel pressure vessels need PWHT?

Usually not for Code purposes. Most austenitic weldments do not require it, and stress relief can sensitize standard-carbon grades. Duplex grades are generally not stress relieved; if heat treatment is required, it is typically a full solution anneal.

Is local PWHT acceptable instead of furnace PWHT?

Sometimes. Division 1 permits local methods for defined geometries, and in a cylindrical shell a nozzle generally needs a full-circumference band. Owners may prohibit it, and a compliant local treatment can relieve less residual stress than a furnace cycle.

What happens if welding is done after PWHT?

The new weld must be evaluated for PWHT on its own. Unless an exemption or limited Code alternative applies, another cycle is needed before the final hydrostatic test, within the procedure qualifications and the simulated-PWHT time on the material certificates.

What PWHT information belongs in a pressure vessel RFQ?

Include the Code, edition, service, materials, thicknesses, weld details and owner PWHT requirements, plus whether local or staged PWHT is acceptable, overall dimensions with nozzles and supports, and inspection, hardness, qualification and record requirements.

Ready to start your next project?